New builds & openings
Pathways roughed in with the contractor, terminated after drywall, tested before the POS vendor arrives.
Field services · Cabling
Most failed POS installs are cabling problems in disguise: a drop that was never run, a jack wired the wrong way, a printer left on Wi-Fi. We cable the counter, the kitchen and the back office so the hardware has something solid to plug into.
Per-station plan
We plan cable by station, not by building. This is the starting point for a typical quick-service restaurant or small store, adjusted on the walkthrough.
| Station | Drops | Notes |
|---|---|---|
| Front counter, each register | 2 | One for the terminal, one for a printer or spare |
| Kitchen display, each screen | 1 | Run to the mount height, not the floor |
| Kitchen printer | 1 | Kept away from heat and grease, in protected pathway |
| Self-order kiosk | 1 | Plus a dedicated outlet behind the unit |
| Access point | 1 PoE | Ceiling mount, placed from a coverage check |
| Camera | 1 PoE | Placed with your security provider |
| Back office | 2 or more | Office PC, router handoff and any spare |
How we cable
The next technician, ours or anyone’s, should be able to read the closet without a phone call.
Projects
Cabling is usually one step inside a bigger change, so we fit around the project that triggers it.
Pathways roughed in with the contractor, terminated after drywall, tested before the POS vendor arrives.
Counters move and kitchens change shape. We relocate drops and retire the ones nobody needs.
A new platform often needs more wired devices than the old one. See the POS replacement checklist.
Common questions
Cat6 is our default for new retail drops. It carries the data each terminal, printer and kitchen screen needs, powers access points and cameras over PoE, and leaves headroom for whatever replaces today’s hardware.
The TIA standard allows a 100 meter channel, which is about 328 feet, including patch cords. Some POS vendors set a shorter limit; Toast, for example, asks for runs under 300 feet.
Yes, and that is the most common job. We finish and test the drops to the vendor’s readiness list so the install day goes ahead. See our Toast site preparation for one example.
Yes. We walk the plans with the contractor, rough in pathways while the walls are open, and come back to terminate and test after drywall, on the contractor’s schedule.
A labeled drop at every station, test results for each cable, a photo of the rack or wall panel and a simple map showing which port feeds which device.
Related services
Station, Mini, Flex and kitchen displays
Cabling, mounts and KDS before go-live
Register, Terminal, Kiosk and KDS
PIN pad swaps for franchise lanes
Workstations, CAPS and network for hotels and venues
Hub, card readers and printers for retail
Terminals and store server for restaurant chains
On-site installs for Shift4 merchants and partners
A skilled technician for your ticket